(S3O-5265) Waverley Railway

18th December 2008

Waverley Railway

9. Rhona Brankin (Midlothian) (Lab): To ask the Scottish Executive what progress has been made in relation to the project to reopen the Waverley line between Edinburgh, Midlothian and the Scottish Borders. (S3O-5265)


The Minister for Transport, Infrastructure and Climate Change (Stewart Stevenson):





We have recently allocated further capital to accelerate a package of advanced works, including taking forward the diversion of key utility services along the route. The purchase of all necessary land is well under way and is expected to be effectively complete around April 2009. Good progress continues with the necessary procurement development for the main works, which will benefit from the acceleration of the advanced works. Contractors and financial investment organisations continue to express a strong interest in the project.


Rhona Brankin: As the minister is aware, the Waverley line will bring great social, environmental and economic benefits to Midlothian and the Borders, including some 360 full-time jobs in the construction of the line and 550 full-time jobs when the line is completed. Can the minister give us some more detail on what funding method will be used for the Scottish Government's contribution to the project? Can he put a figure on the Government's contribution? In addition, given the current economic uncertainty, what discussions have he or Transport Scotland officials had with developers about their financial contribution to the project?


Stewart Stevenson: The railway line will be built, financed and maintained by a not-for-profit company using a design, build, finance and maintenance contract under the non-profit-distributing procurement model. We have previously stated that the costs will be in the range £230 million to £295 million.


Like the member, I very much welcome the 360 or so jobs that will be created during construction and the more than 500 jobs that will result thereafter. Clearly, the contribution of developers is a significant part of the project. We should remember that developer contributions are expected over the life of the project. Discussions with prospective developers have taken place and will continue as the project moves forward.


Jeremy Purvis (Tweeddale, Ettrick and Lauderdale) (LD): I have written to the minister about a business in my constituency that still awaits Transport Scotland's view on how much of the business's land will be required for the construction of the line and whether its land will be required for access during the construction of the line. When the people in that business read the Official Report, are they expected to be happy that they will need to wait another five months for that information to be provided, especially given the current economic climate?


Stewart Stevenson: The member will be aware of the legal environment surrounding compulsory purchase orders and voluntary purchases of land. He should welcome the fact that we have now set a date—April 2009—on which we expect the land acquisition to be complete. That is very rapid and satisfactory progress. I hope that Transport Scotland continues to have meaningful discussions with the business to which the member referred.


Stewart Stevenson
does not gather, use or
retain any cookie data.

However Google who publish for us, may do.
fios ZS is a name registered in Scotland for Stewart Stevenson
www.blogger.com www.ourblogtemplates.com


  © Blogger templates The Professional Template by Ourblogtemplates.com 2008

Back to TOP