20 September 2007

(S3O-656) Aberdeen Western Peripheral Route

20th September 2007
Aberdeen Western Peripheral Route
2. Mike Rumbles (West Aberdeenshire and Kincardine) (LD): To ask the Scottish Executive why it will not make a statement on its intended method of financing the Aberdeen western peripheral route until any public inquiry on objections to the road has been completed. (S3O-656)
The Minister for Transport, Infrastructure and Climate Change (Stewart Stevenson): We will examine the funding of the Aberdeen western peripheral route for its suitability for taking forward under our proposed Scottish futures trust. The procurement of the scheme will proceed as the statutory process takes its course.
Mike Rumbles: I have a letter from Alex Salmond dated 15 June 2007 in which he says that he will ensure that the road
"is not financed by ... PPP/PFI".
Does not the minister accept that by dropping the commitment to a public-private partnership programme, he risks, at least, further delay on top of the one-year delay that he has already announced, and that he might jeopardise the entire project?
Stewart Stevenson: No.
Richard Baker (North East Scotland) (Lab): What is the current estimate of the increase in cost of financing the western peripheral route that will result from the minister's decision to delay its construction by a year? What share of that cost will be borne by council tax payers in Aberdeen and Aberdeenshire?
Stewart Stevenson: The scheme cost remains £295 million to £395 million. The member refers to my announcement of a new date for the completion of the Aberdeen western peripheral route, but I draw to his attention the fact that I inherited every single day of delay, which I reflected in the announcement of a 2012 completion date.
Alex Johnstone (North East Scotland) (Con): I ask the minister to give an assurance that, whatever he decides about the future funding of the project, he will not let his ideological aims and objectives get in the way of its progress and that not a single penny will be added to the tax bill of local taxpayers as a result.
Stewart Stevenson: I am sure that the member knows that, as a north-east member, I share other members' belief in the urgent need to address the issue of traffic in Aberdeen. I will work night and day to ensure not only that we deliver the project that Aberdeen needs, but that we do so at a cost that is affordable and through the use of a funding mechanism that is more effective in cost terms than the discredited PPP system.
Brian Adam (Aberdeen North) (SNP): What further progress has been made on starting the northern leg of the AWPR?
Stewart Stevenson: I am pleased to say that this week detailed ground investigations have commenced on the northern leg. The work will involve the drilling of approximately 100 boreholes and 183 trial pits and the deployment of 30 geotechnical engineers, geologists, drillers, ecologists and archaeologists. That work is firm and real evidence of our determination to make early progress when we can.
Lewis Macdonald (Aberdeen Central) (Lab): Further to Richard Baker's question, I give the minister a third opportunity to say to what extent the additional costs of the project will be borne by local council tax payers. What part of the envelope of £295 million to £395 million will now be paid by council tax payers in Aberdeen and Aberdeenshire?
Stewart Stevenson: I am sure that the member knows that the price range that I quoted, which remains the same, is based on 81 per cent of the costs being met by the Scottish Government, 9.5 per cent of them being met by Aberdeen City Council and 9.5 per cent of them being met by Aberdeenshire Council. There is no change.

Stewart Stevenson
does not gather, use or
retain any cookie data.

However Google who publish for us, may do.
fios ZS is a name registered in Scotland for Stewart Stevenson
www.blogger.com www.ourblogtemplates.com


  © Blogger templates The Professional Template by Ourblogtemplates.com 2008

Back to TOP